{"id":244986,"date":"2024-10-19T16:06:25","date_gmt":"2024-10-19T16:06:25","guid":{"rendered":"https:\/\/pdfstandards.shop\/product\/uncategorized\/bsi-pd-iec-ts-62257-7-32018\/"},"modified":"2024-10-25T11:05:59","modified_gmt":"2024-10-25T11:05:59","slug":"bsi-pd-iec-ts-62257-7-32018","status":"publish","type":"product","link":"https:\/\/pdfstandards.shop\/product\/publishers\/bsi\/bsi-pd-iec-ts-62257-7-32018\/","title":{"rendered":"BSI PD IEC\/TS 62257-7-3:2018"},"content":{"rendered":"

This part of IEC 62257 specifies the general requirements for the selection, sizing, erection and operation of generator sets in decentralized rural electrification systems.<\/p>\n

It applies to all low voltage combustion engine electricity generator sets energized by renewable energy such as biomass gasifier or biogas, or fossil fuel such as gasoline or diesel fuel, and designed for supplying electrical power to isolated sites used in systems as described in IEC TS 62257-2.<\/p>\n

This document is not an exhaustive resource for the design, installation, operation or maintenance of generator sets, but is more focused on recommendations to provide strategies on selection and criteria which may affect the use of such generation systems in a rural electrification project.<\/p>\n

Four cases of micropower plant will be considered as illustrated by Figure 1 to power a collective electrification system (microgrid) or an individual electrification system.<\/p>\n